Location based scheduling and LPS: what each sees

A worked apartment-building example shows how flowlines reveal crew movement and how Last Planner turns that information into workable commitments.

Published · 9 min read · By the Villego team

Your drywall foreman sees a start date for the second floor. Your electrician sees another day of rough-in there. Both schedules look reasonable until the crews meet in the same hallway.

Location based scheduling makes that conflict visible by showing time and place together. The Last Planner® System (LPS) asks a different question: can the people doing the work make and keep the required handoff? You need both views when a believable crew sequence depends on promises that haven't yet been tested.

What location based scheduling and LPS each see

Say your superintendent has a clear floor-by-floor schedule, but the plumbing foreman can't promise Friday's release because a design question remains unanswered. The drawing shows an intended sequence. It doesn't settle that question.

A location-based schedule follows crews through defined work areas. It helps you see production rates, gaps between trades and the consequences of a slower predecessor. LPS connects that plan to the people who can deliver it. A last planner is usually the foreman or other person with direct authority over the work and its resources.

That distinction helps explain the purpose of Villego®, a hands-on Last Planner System simulation in which a project team builds a small house, or "villa," from small bricks in two rounds. Teams first build the usual push way, then the Last Planner way, while observers record construction time, waste, safety, productivity and PPC, or Percent Plan Complete. PPC measures the share of promised assignments completed as agreed.

The relevant lesson for scheduling is the difference between assigning a date and negotiating a workable release. A faster line won't resolve an unanswered request. You still need the conversation.

Line of balance, flowline and location based management

An activity list can contain "electrical rough-in" eight times without showing whether one crew can move continuously between those areas. You'd have to inspect the dates and locations separately to see the pattern.

Wikipedia's "Line of balance" entry, which redirects to "Linear scheduling method," describes graphical scheduling focused on continuous resource use in repetitive activities. The July 2026 revision lists line of balance, flowline and location-based scheduling among related names. Buildings use discrete floors or wings. Highways can use distance along the alignment.

In construction discussion, line of balance and flowline often refer to time-location views of repeating work. Terminology isn't perfectly uniform. The useful idea is that a crew's progress through locations becomes a visible line, with its slope representing the production rate under the chosen axis convention.

Russell Kenley and Olli Seppänen (2010), in Location-Based Management for Construction: Planning, Scheduling and Control, describe a broader location-based management system, or LBMS. It links quantities by location to resource assumptions, scheduling logic and production control. A flowline is one view of that system; a chart alone isn't the complete method.

For example, doubling the framing quantity in a corner wing should change its duration unless capacity changes too. LBMS can accommodate unequal locations. Don't force identical durations just to make the lines parallel. Your location breakdown structure, the hierarchy of building, floor and work area, needs to match actual handoffs.

How to draw a simple apartment-building flowline

A promise to finish "the floor" is hard to interpret if one foreman means the east wing and another means both wings. Agreeing on locations comes before drawing lines.

Consider a hypothetical four-story apartment building in Columbus, Ohio. Each floor contains 12 apartments. For scheduling, split each floor into two wings containing six apartments apiece. That gives 4 × 2 = 8 zones and 8 × 6 = 48 apartments. Number the zones in the agreed crew sequence: first-floor east, first-floor west, then the same order on successive floors.

We're isolating a small interior-work sequence. Assume the building is ready for these crews, one crew serves each package, and framing, coordinated mechanical/electrical/plumbing rough-in and drywall hanging each take two workdays per zone. The rough-in package represents several coordinated trades; it would need more detail in the field.

For framing, assume 480 linear feet of partition layout per zone and a crew rate of 240 linear feet per workday. Duration = quantity ÷ crew production rate = 480 ÷ 240 = 2 workdays. Other packages need their own quantity and capacity checks; they don't inherit framing's rate.

The following procedure works on graph paper or in a spreadsheet:

  1. Put elapsed workdays on the horizontal axis and eight location bands on the vertical axis, numbered from bottom to top. Day 0 starts the first workday. Weekends don't consume these workday units.
  2. Draw framing through each zone for two workdays, moving immediately to the next zone. Its first interval is day 0–2; its last is day 14–16.
  3. Start rough-in one workday after framing finishes in each zone. Start drywall one workday after rough-in finishes. These are provisional protective buffers; required inspections and other release conditions still need separate checks.
  4. Plot each package's start at a zone's lower boundary and finish at its upper boundary. Join successive intervals to show the package's progression across the building, and choose a different line style for each package. Keep the dates beside the drawing so nobody mistakes a diagonal for permission to enter a partly finished zone.

Here's the date table you'll use to check the plotted lines:

ZoneFramingRough-inDrywall hanging
1: Floor 1 east0–23–56–8
2: Floor 1 west2–45–78–10
3: Floor 2 east4–67–910–12
4: Floor 2 west6–89–1112–14
5: Floor 3 east8–1011–1314–16
6: Floor 3 west10–1213–1516–18
7: Floor 4 east12–1415–1718–20
8: Floor 4 west14–1617–1920–22

The same calculation generates every framing interval: zone number minus one, multiplied by two, gives its start; add two for its finish. Rough-in starts three workdays after framing starts, and drywall starts six workdays after framing starts.

This sequence ends at elapsed workday 22. That's the end of drywall hanging in this example, not apartment completion. Taping, finishes and commissioning aren't included. We haven't scheduled the whole building.

How to read rates, buffers and deviations

Suppose rough-in takes three workdays per zone instead of two. The original dates won't hold up.

With time horizontal and location vertical, a steeper ascending line indicates faster movement across the sequence of zones. Our plan advances at 1 ÷ 2 = 0.5 zones per workday. The slower rough-in rate is 1 ÷ 3 = one-third of a zone per workday. Its line becomes flatter, and following trades approach it.

If rough-in still starts at day 3 and continues at that slower rate, its first zone finishes at day 6 rather than day 5. The protective buffer before drywall is gone. Zone 3 finishes at day 12, but drywall is scheduled to enter at day 10. That's a two-workday conflict before allowing any additional release requirement.

Look at occupied intervals, not just crossings. Lines can remain apart while a buffer has already disappeared. A gap can also be intentional, for drying or inspection, rather than evidence of wasted space.

You'd plot actual progress separately from the plan, then extend a forecast using a stated rate assumption. A flatter actual line suggests slower movement; a line shifted right with the original slope suggests a late start followed by the planned pace. A pause shows lost continuity.

Record installed quantities and crew hours too. Production rate is output per time; labor productivity is output per labor hour. They aren't interchangeable. Adding workers might improve a daily rate while reducing labor productivity, especially in a crowded corridor. Partial work isn't an automatic zone release. The receiving trade must agree to any smaller handoff before you count it as available space.

How the weekly LPS conversation uses the flowline

At your weekly meeting, the drywall foreman can see the zone 3 conflict. But the line doesn't explain whether rough-in slowed because of staffing, missing materials or an unresolved design detail. The team must establish that before choosing a response.

Seppänen, Ballard and Pesonen (2010), in The Combination of Last Planner System and Location-Based Management System, propose combining the systems across master, phase, look-ahead and weekly planning. Their Lean Construction Journal paper recommends using LBMS forecasts as an information source for commitments, without expanding the flowline to every individual assignment. The proposed processes still needed testing in practice.

For your building, that means reviewing actual releases and the revised forecast together. The rough-in foremen explain their capacity and constraints. The superintendent checks whether changed sequencing would create congestion elsewhere. Who will make the recovery happen? A revised line needs an accountable action behind it before the team can reasonably rely on its prediction for the next handoff.

The look-ahead schedule supports make-ready, the process of clearing constraints before work is due. You'd use the forecast to identify threatened zones, then check materials, information and safe access. A predicted release isn't proof of readiness.

Next, the last planners negotiate the weekly work plan. "Hang drywall in first-floor east apartments after rough-in acceptance, complete by Friday" needs a named owner and an agreed completion condition. If that release can't be secured, the crew needs another ready assignment or a revised commitment. A workable backlog is ready work available as an alternative, not any task you can start somewhere else.

Afterward, compare completed commitments with production movement. Eight completed assignments out of ten gives PPC = 8 ÷ 10 × 100 = 80%. That score doesn't tell you how many zones advanced. Reasons for variance, the explanations for missed commitments, and the flowline together show what to change. Don't replace one measure with the other.

Where the extra structure pays off, and where it costs

A repeating apartment fit-out can justify detailed location tracking. A single elevator inspection won't become clearer because you've squeezed it onto a sloping line.

LBMS asks for quantities by location, credible rates and frequent progress updates. That's work. Use common location names across the schedule and weekly assignments so the team doesn't report the same progress twice under different labels. Keep procurement and one-time milestones linked through schedule logic even when they aren't visible as flowlines.

Your critical path method (CPM) schedule can still serve contractual milestones and dependency reporting. CPM and LBMS can work together. The 2010 paper describes integrating CPM logic into flowline scheduling, rather than treating the two methods as competing choices for every scheduling need. And LPS covers collaborative planning as well as weekly promises; it isn't just a meeting added after technical planning.

Equal zone durations make this example resemble takt planning, which organizes work around a shared beat. LBMS can instead model different rates and unequal quantities. Neither approach excuses unsafe overlap or bypassed inspections. Smaller zones help only when crews can actually release them independently.

Use the forecast to improve the next handoff

When rough-in slips, don't ask drywall to promise the original date simply because it's on the chart. Recheck the release and its downstream effect first.

Start with one phase where location conflicts matter, such as apartment interiors. Agree on zones with the foremen, draw the intended flow and compare actual movement with commitments each week. You'll learn whether the location detail earns its upkeep.

The flowline makes a threatened handoff visible. LPS gives the people responsible a way to test it, make work ready and agree on what they'll deliver next. Keep those functions connected, and your forecast becomes useful input to a promise rather than a substitute for one.

Sources

  1. Wikipedia (2026). Linear scheduling method.
  2. Russell Kenley and Olli Seppänen (2010). Location-Based Management for Construction: Planning, Scheduling and Control.
  3. Olli Seppänen, Glenn Ballard and Sakari Pesonen (2010). The Combination of Last Planner System and Location-Based Management System.