The Last Planner® System simulation for construction teams info@villego.com

Weekly work plan: commitments your crews can keep

Write crew commitments that match ready work and available capacity. Use a practical meeting agenda, a construction example, and PPC to improve the next plan.

Updated · 13 min read · By the Villego team

Your drywall foreman says the second floor will be ready Friday. The electrician hears Wednesday. Both leave the trailer believing they've agreed, and neither has checked whether the inspection is booked. A weekly work plan can look convincing while leaving the next crew guessing.

In the Last Planner® System (LPS), weekly work planning turns ready work into explicit commitments from the people directing production. You'll need more than task names and finish dates. This guide explains how to write checkable assignments, negotiate reliable promises, and learn from the work that doesn't finish as agreed.

What belongs in a weekly work plan?

“Continue second-floor rough-in” doesn't tell another trade when it can start. It doesn't tell your foreman what counts as complete, either. A useful weekly work plan records who promises what work, in which location, by when, and with what completion conditions.

The last planner is the person closest to production with authority to commit the crew, usually a trade foreman or superintendent. Your plan should reflect that person's assessment of ready work and capacity. A scheduler can record the commitment; they can't manufacture it.

Teams can practice this distinction with Villego®, a hands-on Last Planner System simulation in which a project team builds a small house, or “villa,” from small bricks in two rounds. First they use the usual push approach, then the Last Planner approach, while observers record construction time, waste, safety, productivity and PPC. The contrast gives teams a shared setting for discussing why a busy crew can still leave its customer waiting.

Warcup and Reeve (2014) describe weekly planning and PPC instruction within the simulation. They also caution that participants need further study and practice to apply LPS on real projects. You'll still need site-specific judgment.

Keep the weekly plan distinct from the master schedule. The master schedule sets project obligations; the weekly plan records the near-term promises that support them. Hiding a milestone problem behind easy weekly tasks won't solve it.

Select sound work from the workable backlog

Say a general contractor in Columbus, Ohio, is building a hypothetical four-story medical office building with 14 trade partners. The schedule calls for overhead duct installation, but the approved support detail is missing. A new row won't clear it.

Make-ready means removing the constraints that prevent work from starting or finishing as intended. Your look-ahead schedule supports that preparation before the weekly meeting. The workable backlog is the pool of work that has passed readiness checks and can be performed, rather than a list of overdue activities.

Choose commitments only from sound work. Check drawings and approvals, prerequisite work, material availability, qualified labor, equipment, access and safe working conditions. “It should arrive Monday” isn't evidence that a missing component is available. Record a constraint-removal action separately; don't present an installation dependent on an unresolved constraint as a firm promise.

Then prioritize ready work by the project's required handoffs, meaning the transfer of an agreed work area or output to its next user. An available task doesn't automatically deserve priority.

Keep some lower-priority ready work as backup. Ballard uses workable backlog for these additional quality assignments; Mossman calls them Plan B. Don't count backup tasks as promised production unless the crew actually commits to them. If the priority work isn't ready, expose the schedule impact and assign recovery actions instead of quietly filling the sheet with easier work.

Test assignments against Ballard's five criteria

In the Columbus example, “rough-in exam rooms” could mean every room, one corridor, or whatever the crew manages. That ambiguity makes both coordination and measurement unreliable.

Ballard (2000), in The Last Planner System of Production Control, lists Definition, Soundness, Sequence, Size and Learning on pages 3-17 and 3-18. The first four test the proposed assignment. Learning asks whether unfinished assignments are tracked and their reasons identified. It belongs in the planning cycle, rather than being another prerequisite you can clear before starting.

Definition: can everyone recognize completion?

“Work on room rough-in” is too loose. Try “Install and self-check electrical boxes and conduit in rooms 201–212 by Wednesday at 3 p.m., to the approved drawings, with inspection documentation ready.”

Your receiving trade should understand that boundary. Include the quantity or room limits, responsible foreman, due time and evidence of completion. If inspection is part of the promised result, specify its scope and approval deadline rather than assuming somebody will arrange it. Don't confuse inspection readiness with approval.

Soundness: can the crew execute the whole assignment?

Boxes on site won't help if room layouts are unresolved. Ask what evidence supports each readiness check: the approved drawing revision, confirmed access, completed predecessor work and available equipment.

A verbal assurance may be enough for a minor coordination detail. It isn't enough for a missing design decision. Where work depends on an earlier commitment within the same week, show that dependency and check its readiness too; don't hide it inside an apparently unconditional promise.

Sequence: is this the right work now?

Installing corridor ceilings before above-ceiling checks can create rework even when the ceiling materials are ready. The sequence must serve both the crew's construction method and its customer, often the next trade.

Use the agreed pull planning sequence to check priorities, then review shared space and equipment as well as predecessor dates. That narrow corridor won't accommodate both.

Size: can this crew deliver a useful handoff?

A promise covering all second-floor rough-in may be too large to finish or diagnose. Split it into work areas the next crew can use without returning later to finish missing pieces or reopening completed work. Avoid tiny administrative fragments created just to increase the completion count.

For a hypothetical capacity check, assume three electricians have seven productive hours each per day over three days. Available capacity is 3 × 7 × 3 = 63 person-hours. If 12 rooms require an estimated five person-hours each, demand is 12 × 5 = 60 person-hours, leaving three person-hours. That margin is thin. The foreman should check recent comparable output and known interruptions before committing; these assumptions aren't an industry production rate.

Learning: will a miss change the next plan?

If the rooms miss Wednesday, “electrical late” won't help next week. Record the unmet promise and the specific reason. Was access blocked, the estimate wrong, or required information missing?

Agree on a countermeasure with an owner and due date. Learning should change something tangible, such as checking room release before commitments or adjusting assignment size. Otherwise, you'll repeat the same miss with a cleaner spreadsheet.

Make and secure a reliable promise

A foreman who says “we'll try” hasn't promised the receiving crew a usable handoff. And a superintendent who writes a finish date without asking hasn't secured agreement.

Mossman (2020) explains that last planners promise after clarifying conditions of satisfaction, including the due date, and checking that they can perform the work. Conditions of satisfaction are the agreed requirements that make the result acceptable to its customer. Once finished, the performer declares delivery so the customer can assess the result against the conditions both parties accepted before the work started, rather than an expectation introduced at handoff.

For the Columbus rooms, the drywall foreman could request electrical release by Wednesday afternoon. After checking resources, electrical proposes rooms 201–212. The corridor is excluded. The drywall foreman confirms that this package supports the planned start. Now there's a defined promise to record.

The person securing the promise has work to do, too. You'll need to state the request clearly, listen to the proposed boundary, and verify that the receiving crew accepts it. Don't treat silence as consent. Ask for an explicit commitment after conflicts are resolved.

Mossman also stresses the freedom to say no. A foreman who can't decline an unsound request may agree publicly while expecting failure privately. You'll get better information by allowing a counteroffer, a smaller package, or a refusal tied to an unresolved constraint.

Keep the delivery conversation open. If the foreman discovers that Wednesday is at risk, they should notify the receiving trade immediately and negotiate the response. A revised forecast helps coordination; it doesn't erase the original promise or its learning value.

Run a weekly planning meeting that ends in agreement

If your mechanical foreman first hears about a shared lift conflict during the meeting, everyone waits while details are checked. Preparation determines how much of the session can be spent making decisions.

Invite the last planners for active work and affected handoffs, the GC superintendent, and the person coordinating make-ready actions. Include a project manager when resource or contractual decisions need their authority. Designers, suppliers or inspectors can join for specific unresolved interfaces; they don't all need to sit through every production discussion.

Each foreman should bring a proposed plan, readiness evidence, crew availability and status of current commitments. Your facilitator needs the previous plan, PPC results, outstanding constraints and relevant milestone dates. Resolve routine questions beforehand where possible.

Mossman (2020) says commitment planning involves all last planners and generally lasts less than an hour, even on large projects. A practical starting agenda is 50 minutes. That's a facilitation recommendation, not a fixed LPS requirement:

  1. Confirm current status, 5 minutes. Identify changes that affect next week's starts, such as an area release slipping into Monday.
  2. Review promises and learning, 10 minutes. Check completed assignments, PPC and reasons for misses. Confirm the action taken on a repeated problem.
  3. Check readiness and priorities, 10 minutes. Compare proposals with the workable backlog and required handoffs. Keep unresolved make-ready actions visible but separate.
  4. Negotiate the plan, 20 minutes. Resolve space and resource conflicts, check capacity, and agree completion conditions with receiving trades.
  5. Confirm commitments, 5 minutes. Read back the final promises, responsible people and due times. Confirm Plan B and distribute the agreed version.

The time budget is 5 + 10 + 10 + 20 + 5 = 50 minutes. If you routinely exceed it, check whether the meeting has become the place for discovering constraints rather than confirming ready work.

Schedule the session before the plan period starts, with enough time for crews to organize resources. Thursday can work for a Monday start if current-week status is clear. Sunday shouldn't become unpaid preparation time.

Use a wall board, paper form or shared spreadsheet that crews can access. Software choice matters less than one identifiable, agreed version. After the meeting, each foreman should explain the commitments to their crew; attendance alone doesn't communicate the plan to the field.

A hypothetical weekly work plan for the Columbus project

Suppose the Columbus team puts “second floor complete” on one line. Several trades could report progress without delivering any usable room package. Separate promises make the handoffs visible.

The table below is a hypothetical five-assignment excerpt for a Monday–Friday week, not the project's entire plan. All names, quantities and readiness checks are illustrative. Approved information, safe access and required resources have been checked before commitment.

IDPromisor and crewLocation and promised outputPlanned work / due timeReadiness evidence and completion check
W1Maya, electrical, 3 peopleRooms 201–212: boxes and conduit installedMon–Wed / Wed 3 p.m.Layout and framing released; materials on site; self-check recorded and inspection documents ready
W2Luis, plumbing, 2 peopleRooms 213–218: water rough-in installed and testedMon–Tue / Tue 2 p.m.Supports and access released; fittings available; specified test recorded
W3Erin, mechanical, 4 peopleWest corridor: 80 feet of overhead duct installedMon–Thu / Thu noonSupport detail approved; exclusive lift slots agreed; supports and joints checked
W4Sam, GC superintendentRooms 201–212: electrical inspection and release securedThu / Thu noonInspector booking confirmed; depends on W1 delivery; approval recorded before enclosure
W5Dana, drywall, 4 peopleRooms 201–212: agreed wall faces closedThu–Fri / Fri 3 p.m.Boards staged; depends on W4 approval; specified faces complete, checked and cleaned

W4 and W5 have explicit same-week dependencies. Their promisors must assess those upstream promises, not assume that calendar dates clear the work. If W1 is at risk, W4 and W5 need an early discussion. Drywall mustn't start enclosure without the required release.

A separate Plan B could cover already released rooms 221–224. Check that it won't steal Dana's crew from W5 or disrupt another trade. Backup work is an option, not hidden extra capacity.

For a reusable template, keep these columns and add actual completion, met or missed, and reason for variance. Reasons for variance explain why delivery differed from the promise. In Excel, one assignment per row makes review easier. Keep detailed methods and inspection records elsewhere, with enough reference information for the crew to find them.

What if a trade won't commit?

Suppose the electrical foreman refuses W1 because their company hasn't confirmed the three-person crew. Drywall would inherit an undisclosed staffing risk.

First distinguish inability to promise from refusal to participate. Ask what prevents a commitment. Missing resources, unclear scope, disputed access and lack of authority require different responses. You can't solve them all by repeating the deadline.

If the concern is legitimate, record the requested work as uncommitted and name who will resolve the issue by when. Negotiate a smaller ready package where that would still help the next trade. Don't accept a token promise that leaves the required handoff uncovered.

If the foreman lacks authority, involve the trade's manager and clarify who may commit resources. If repeated failures by the GC have damaged trust, the GC needs to keep its own make-ready promises. A lecture about collaboration won't repair an unreliable room-release process.

But sometimes the trade won't engage despite clear requests and available work. Project leadership should address persistent nonparticipation privately, with the trade's manager and through the applicable contract process, rather than using the planning room to argue about sanctions. Keep accurate records of requests, responses and schedule effects. LPS doesn't replace contractual obligations, and this discussion isn't legal advice.

Don't force a yes for the board. Show the uncommitted handoff and its milestone risk, then work with affected trades on recovery options. Work never promised doesn't belong in the PPC denominator, but it must remain visible in schedule review. Otherwise, a high PPC could hide a serious coverage gap.

Check promises with PPC without rewriting history

Suppose W1 through W4 meet their agreed conditions and due times, while W5 finishes only some wall faces. W5 still counts as a miss.

Percent Plan Complete (PPC) is the percentage of promised assignments completed as agreed. For this hypothetical excerpt, PPC = 4 completed assignments ÷ 5 promised assignments × 100 = 80%. Count assignments, not installed quantities or labor hours. Partial completion doesn't earn partial credit for an unchanged assignment.

Agree the measurement rules before the week starts. Preserve the original plan and keep a separate change record if new work is added or a promise is renegotiated. Record the circumstances of a cancellation instead of deleting an inconvenient row after the event. Report extra work separately so it can't make a missed original promise disappear.

Use your daily huddle to check handoffs and raise emerging risks while there's still time to respond. Review misses together at week's end. Carry the countermeasures into the next plan.

Mossman (2020) warns that using PPC for purposes other than learning encourages score manipulation. Don't rank trades from isolated percentages. Check priority handoffs and milestone progress alongside reliability; completing easy work won't recover a delayed inspection sequence.

A useful plan makes the next crew's start believable

If drywall still can't tell you which rooms will be released and when, the weekly plan needs another conversation. More detailed formatting won't resolve an uncertain promise.

For your next cycle, take one contested assignment and test its definition, readiness, sequence and size with both the producing foreman and the receiving trade. Confirm the promise, then check delivery and learn from any miss. That's a manageable place to start.

The standard is a believable handoff backed by ready work and honest capacity. Keep unresolved work visible, allow people to decline unsound requests, and protect the original record. Crews need a usable plan when conditions change.

Sources

  1. Herman Glenn Ballard (2000). The Last Planner System of Production Control.
  2. Alan Mossman (2020). Last Planner: 5 + 1 crucial & collaborative conversations for predictable project production planning.
  3. Robert Warcup and Edward Reeve (2014). Using the Villego® Simulation to Teach the Last Planner® System.