Your Friday report says the crews were busy. Monday's coordination meeting tells a different story: the electrician can't start because the promised wall inspection never happened. Percent plan complete makes missed promises visible.
In construction, PPC means percent plan complete: the percentage of planned assignments completed as promised. It's a plan-reliability measure used in the Last Planner® System (LPS), a collaborative approach to production planning. It doesn't tell you what percentage of the building is finished.
The useful question is what you'll change after a promise is missed. If your team treats PPC as a score to defend, you'll get cleaner reports without necessarily getting better handoffs. A handoff is the release of work from one crew to the next. That's what reliable planning needs to protect.
What percent plan complete should help your team learn
Say a foreman reports a task as complete because installation is finished, while the next trade still needs an inspection before starting. Both people may believe their answer is reasonable. Your PPC discussion needs to expose that disagreement before it becomes another missed handoff.
Villego® is a Last Planner System simulation in which a project team builds a small house, or “villa,” from small bricks in two rounds: first the usual push way, then the Last Planner way. Observers record construction time, waste, safety, productivity and PPC. Comparing the rounds gives participants a shared experience for discussing why promises were kept or missed.
Warcup and Reeve (2014), in Using the Villego® Simulation to Teach the Last Planner® System, identify teaching participants to calculate PPC as one of the most important facilitator tasks during weekly planning sessions. They connect tracking PPC with identifying root causes and choosing countermeasures. Their qualitative study involved two participant groups; it doesn't establish a guaranteed field-project improvement.
The practical lesson is straightforward. Teach the counting rule alongside the learning conversation. A last planner, usually the foreman or supervisor closest to the work, should understand what was promised and what prevented delivery. Otherwise, you've taught arithmetic without changing planning behavior.
How do you calculate PPC?
A superintendent can produce an impressive percentage by counting every finished activity, including work nobody promised. That answers the wrong question. PPC compares completed commitments with the commitments in the agreed weekly work plan.
PPC = assignments completed as promised ÷ total assignments promised × 100.
Use assignment counts, not physical-progress percentages. Each assignment earns either one completed promise or zero. The due date and agreed completion conditions matter as much as installed quantity.
Here's a hypothetical example. Say a general contractor in Columbus, Ohio, is building a four-story medical office building. Its weekly plan contains 16 assignments, each with a responsible foreman, defined location and promised release date.
| Trade | Assignments promised | Complete as promised | Not complete as promised |
|---|---|---|---|
| Electrical | 5 | 4 | 1 |
| Plumbing | 4 | 3 | 1 |
| Drywall | 4 | 2 | 2 |
| HVAC | 3 | 3 | 0 |
| Total | 16 | 12 | 4 |
The working is:
- Planned assignments: 5 + 4 + 4 + 3 = 16.
- Completed assignments: 4 + 3 + 2 + 3 = 12.
- PPC: 12 ÷ 16 × 100 = 75%.
Four commitments weren't delivered as agreed. That doesn't mean a quarter of the project's installed work was lost. A short inspection assignment and a larger installation assignment each count once, so PPC can't substitute for quantity or labor-productivity reporting.
One drywall task is nearly finished, but its agreed inspection isn't complete. It earns zero. An extra plumbing task finished during the week isn't in the numerator because it wasn't among the original commitments. Record that useful work separately; don't use it to replace a missed promise.
If no assignments were promised, PPC is undefined. Report “no commitments” rather than inventing 0% or 100%, then investigate why the plan was empty.
What counts as complete, partial or changed work?
In the hypothetical Columbus project, “finish second-floor rough-in” could mean installation only to one person and installation plus testing to another. The resulting argument isn't a math problem. Your completion definition was weak.
Ballard and Howell (2003), in An Update on Last Planner, recommend customer acceptance as the measure of release and measuring PPC against the planned day rather than only the week. In a trade handoff, the receiving crew is the customer of that release.
You can make that concrete before the week starts. An assignment might read: “Complete and test restroom water piping in Zone B, obtain the agreed inspection release, and hand the area to drywall by Thursday.” You'll know what evidence closes it.
Partially completed tasks count as not complete, even at 90% installed. Keep physical progress in a separate field. The missing portion may be exactly what the successor needs, so fractional credit would hide an unreliable release.
Friday completion doesn't rescue a Thursday promise. Early work needs agreed release rules too: completing something sooner doesn't help if it occupies space needed by another crew. Don't silently redefine the due date.
For a task spanning several weeks, agree useful weekly releases that the receiving crew can actually use before committing. Don't redraw assignments after missing them. Legitimate breakdown makes work easier to coordinate; retrospective breakdown changes the score.
When an owner change cancels a promise, retain the original plan and record what was canceled, by whom and on what date. A clear project convention can preserve original-commitment PPC and show any adjusted view separately. Don't erase the evidence. Carryover work needs a new promise for the next period, but completing it later doesn't repair last week's result.
Read PPC trends alongside the work released
Suppose your hypothetical project records 75% one week and 88% the next. The rise might reflect better preparation. It might also reflect fewer commitments or smaller assignments. You won't know from the percentage alone.
A weekly trend should retain completed and promised counts, the reporting period, and notes explaining meaningful changes. Mark shifts in phase, task breakdown or completion rules. Those changes can make before-and-after percentages misleading.
Ballard and Howell (2003) recommend emphasizing the direction and rate of change in PPC rather than its absolute level. They also recommend praising learning instead of blaming failure. That's a better basis for a review than ranking foremen whose crews face different dependencies.
Counts matter when you combine results. In another hypothetical example, a small plan delivers 4 of 4 promises, or 100%, while a larger plan delivers 28 of 40, or 70%. Averaging those percentages gives 85%, but the combined result is (4 + 28) ÷ (4 + 40) × 100 = 72.73%, rounded to two decimals.
Pool assignment counts when you want combined PPC. Retain the separate trends too, because the pooled number can conceal a recurring problem in one work area.
What is a good PPC score? There's no universal pass mark that proves your project is healthy. You're aiming to keep credible promises, but a high score can't establish that crews delivered the work needed for the next milestone.
Review several periods rather than celebrating one week. If PPC rises while inspections or critical handoffs keep slipping, examine the work selected. If it falls after the team starts recording missed promises honestly, you've improved visibility, though delivery still needs attention. Don't punish the disclosure.
Turn reasons for variance into specific countermeasures
“Material late” is a familiar entry in a missed-promise log. It tells you almost nothing about what to change. On the Columbus example, late pipe fittings could reflect an order placed too late or a delivery rejected because nobody arranged unloading access.
Reasons for variance are recorded explanations of why execution differed from the commitment. Categories help you spot repeated problems, but they aren't root causes. Your team needs both a useful category and a short factual account of each missed assignment.
These are practical starting categories, not a universal coding standard:
| Category | Example of a missed promise | Question for the review |
|---|---|---|
| Design or information | Approved detail unavailable | When was the missing decision identified? |
| Materials or delivery | Correct fittings absent | Was ordering or site receipt the failure? |
| Predecessor or access | Area not released by another trade | Were release conditions agreed and checked? |
| Crew capacity or equipment | Committed crew or lift unavailable | What changed after the commitment? |
| Quality or rework | Test failed before release | Which defect prevented acceptance? |
| Safety, weather or site conditions | Safe access unavailable | What was foreseeable before promising? |
| Scope or priority change | Owner redirected the work | Who changed the commitment, and when? |
| Planning or task definition | Assignment exceeded available capacity | What assumption made the promise unrealistic? |
The planning category shouldn't become a place to park unexplained misses. “Other” needs a written account too. Otherwise, you'll build a chart of labels rather than evidence.
Alan Mossman (2015) recommends studying recurring reasons and investigating individual cases. Similar labels can conceal different causes. He illustrates this with two late material deliveries arising from different problems. His guidance supports using a histogram or Pareto chart, which ranks categories by frequency, to focus attention without assuming that frequency alone defines project impact.
A rare missed inspection may block more successor work than several minor installation misses. Choose cases using frequency and consequence. You don't need a full investigation for every small variance.
For the unloading example, root cause analysis in construction can follow the evidence from rejected delivery to missing logistics approval. A countermeasure might require confirmed unloading access before the delivery booking is accepted. Give that action an owner and a due date, then check the next comparable delivery. “Coordinate better” doesn't specify a changed process.
Why making PPC a target encourages gaming
Imagine a hypothetical project manager announces that every trade must exceed 90% PPC to avoid a poor review. A foreman can protect the score by promising less work, leaving difficult handoffs off the plan or stretching due dates. None of those actions necessarily improves production.
The risk follows Goodhart's law: a measure can lose its usefulness when it becomes a target. Wikipedia attributes the original observation to Charles Goodhart (1975) and the familiar measures-and-targets formulation to Marilyn Strathern (1997). Under pressure, people can redefine promises.
Mossman (2015) explicitly warns that PPC is easy to manipulate and says its purpose is learning. He also cautions against interpreting trade scores in isolation because one team's actions affect another's performance.
You can still expect people to keep commitments. Accountability belongs in honest promising, early warning and corrective action, rather than a bonus attached to a percentage. Don't confuse a missed promise with permission to ignore the handoff.
A useful safeguard is to keep task definitions and original commitments visible. Review the required phase work beside the weekly plan, and ask why an essential release wasn't selected. Compare changes in workload with changes in PPC before claiming improvement.
And honest misses shouldn't threaten anyone. A team that exposes uncertainty early gives you time to respond. A team that hides it leaves the same risk on site.
Use tasks anticipated and tasks made ready beside PPC
A hypothetical crew keeps every weekly promise but repeatedly discovers next week's work too late to order materials. PPC can look healthy while the preparation process remains weak. You need a view upstream of execution.
Hamzeh, Ballard and Tommelein (2012), in Rethinking Lookahead Planning to Optimize Construction Workflow, describe tasks anticipated (TA) and tasks made ready (TMR) as complementary lookahead measures. Their definitions use specified planning snapshots, so the comparison horizon matters.
TA asks how much of the current weekly plan was anticipated earlier. In their worked example, 14 of the weekly plan's 18 tasks appeared on the lookahead plan two weeks earlier: 14 ÷ 18 × 100 = 77.78%, reported as 78% in the paper.
TMR assesses how successfully previously anticipated work survives through preparation to execution. Their TMR(2,0) example compares the earlier two-week snapshot with the executed plan: 11 of 20 earlier tasks were completed, giving 11 ÷ 20 × 100 = 55%. This particular measure uses completed surviving tasks, not simply tasks somebody marked ready before starting.
The denominator differs from PPC. Their same example gives PPC of 13 ÷ 18 × 100 = 72.22%, reported as 72%. The figures describe different questions about the same planning process.
Don't mix TMR definitions between reports. Record the horizon, numerator and denominator beside the metric, especially if your readiness log uses a pre-execution readiness measure instead of the paper's executed-task comparison.
For PPC in lean construction to support learning, those upstream findings need action. Low TA suggests work is arriving without enough advance preparation. Low TMR points you toward tasks that were anticipated but didn't reach execution as intended.
Use your look-ahead schedule to identify that work, then track make-ready, the process of removing obstacles before execution, through constraint analysis. A constraint is an unresolved condition preventing the task from proceeding. Neither metric removes it for you.
A PPC review should finish with a tested change
In the Columbus example, another report showing 75% won't stop the next rejected delivery. A PPC construction report earns its place when the team can connect a missed promise to a change in how work is prepared or released.
A short recurring review can follow this sequence:
- Confirm each original assignment against its due date and completion evidence with the responsible last planner and receiving trade.
- Calculate PPC and retain the promised and completed counts beside the trend.
- Record factual reasons for missed promises, then select a recurring or high-consequence case for investigation.
- Agree a countermeasure, an owner and a check date. Check whether the next comparable task improves.
You'll still need installed quantities, productivity measures and milestone forecasts. PPC doesn't replace them. It tells you how reliably your team delivered the assignments it chose to promise.
Keep the score honest and the discussion specific. The result worth pursuing is a better next handoff, supported by evidence that your team learned from the last one.
Sources
- Robert Warcup and Edward Reeve (2014). Using the Villego® Simulation to Teach the Last Planner® System.
- Alan Mossman (2015). Last Planner®: 5 + 1 crucial & collaborative conversations for predictable design & construction delivery.
- Glenn Ballard and Gregory A. Howell (2003). An Update on Last Planner.
- Farook Hamzeh, Glenn Ballard and Iris D. Tommelein (2012). Rethinking Lookahead Planning to Optimize Construction Workflow.
- Wikipedia (2026). Goodhart's law.