Use trade colors and separate symbols to make your pull planning wall readable. Standardize note fields, board layout and the record you share afterward.

Published · 9 min read · By the Villego team

A foreman points at a yellow note and asks, “Is that electrical work or an inspection?” Someone else thinks yellow means a constraint. Your pull planning sticky notes have become a code only the scheduler understands.

That confusion costs meeting time. Worse, it hides who owes what to the next crew. You don't need more colors to fix it. You need one shared rule for ownership, a separate rule for special events, and handwriting the person at the back can read.

This guide focuses on the physical wall. For the wider process of negotiating work backward from a milestone, see the pull planning guide.

Give pull planning sticky notes one color job

Say a general contractor in Columbus, Ohio, is planning the second-floor close-in of a medical office building. The plumber uses blue, but an inspector also uses blue for approval notes. From across the room, responsibility looks identical. That's the problem to solve first.

Villego® is a hands-on Last Planner® System simulation in which a project team builds a small house, or “villa,” from small bricks in two rounds: first the usual push way, then the Last Planner way. Observers record construction time, waste, safety, productivity and PPC, or Percent Plan Complete, the share of weekly commitments completed. The kit includes six colors of sticky notes for pull planning. These provide a way to practice trade ownership and handoffs, the agreed transfer of usable work to the next trade.

Warcup and Reeve (2014) describe different trade colors and predecessor-successor handoff discussions in the simulation. Their account supports using the notes to structure a conversation, rather than decorating a schedule.

For activity notes, I'd use one color per trade. Keep that assignment throughout the phase and display a legend with the trade's name and abbreviation. For our hypothetical board, blue could mean plumbing, pink electrical and green HVAC. There's no universal trade palette.

An alternative is to reserve colors for milestones, constraints and handoffs, leaving activities on neutral paper. That works when event type matters more than scanning trade flow, but you'll need prominent trade labels on every activity. Don't switch between these schemes mid-meeting.

On a trade-colored wall, separate event type from ownership:

ItemSuggested treatmentMeaning to write explicitly
Trade activityAssigned trade color; normal orientationTrade abbreviation and activity ID
MilestoneNeutral card; heavy border; label MAccepted condition and required date
ConstraintNeutral card; label C; separate laneMissing prerequisite, action owner and clear-by date
HandoffLabel H at the connection between activitiesDelivering trade, receiving trade and acceptance condition

Color can't carry everything. Labels help people with color-vision differences and keep meaning intact in grayscale copies. Wikipedia's “Visual control” (2024 revision) describes shared visual cues and an action component. Your legend should explain what people must do when they see a C, not just what C means.

What belongs on each activity note?

“Finish plumbing” doesn't tell the drywall foreman which rooms are available. Nor does “two days” reveal whether the estimate assumes two workers or six. Those omissions create different plans in different people's heads.

A useful card answers the receiving trade's questions. I'd place duration at top left, crew size at top right, the activity and location in the center, and the required predecessor condition below. Put the trade abbreviation and a unique ID along the edge. Keep these positions consistent so readers don't have to hunt.

For the Columbus example, a card could read: “PL-07; pressure-test domestic water, Level 2 east; duration 2 working days; crew 3; need rough-in complete, capped and accessible from PL-06; release: test accepted and record available.” The release describes what the next trade can rely on. It isn't enough to write “done.”

Crew size is people, not labor-hours. With hypothetical eight-hour shifts, this card assumes 3 people × 2 days × 8 hours = 48 labor-hours. That calculation doesn't prove the duration is achievable. Ask the trade foreman to confirm access, equipment and inspection availability before accepting it.

Each note needs a checkable finish. If east and west areas have different release conditions, split them. And don't bundle unrelated work.

If an inspection slot remains unconfirmed, the need is still open. Give that constraint a C identifier and reference the constraint log for its owner and clear-by date. A tidy activity card shouldn't conceal unresolved make-ready work, the work of removing prerequisites that would otherwise block production.

Choose size and handwriting from the back of the room

A beautifully written card can still be unreadable from the doorway. Say your superintendent can read its activity name but can't distinguish “2 days” from “7 days.” You'll lose the discussion as people crowd forward.

For a trial layout, start with 4-by-6-inch notes where several fields are needed. Three-by-three-inch notes suit shorter entries but may force small writing. Wikipedia's “Post-it note” (2024 revision) describes re-adherable paper and lists both sizes; it doesn't prescribe a construction-board standard.

Use a dark marker, plain printed letters and a horizontal format, with the adhesive strip along the top. You'll get more room for activity text. Keep durations in agreed working-day units and write “crew 3,” rather than an unexplained 3. Avoid cursive and pale ink.

Test a completed sample at the farthest seat. If someone can't read it, enlarge the note or shorten the wording without removing the handoff condition. A preprinted grid can help, provided its boxes leave enough writing space.

Don't rotate activities to indicate delay. Rotation makes fields harder to scan and photograph. Use explicit labels instead. Try the adhesive on the actual clean board surface before the meeting; fallen notes lose their position and can silently change the apparent sequence.

Lay out the pull planning board backward from the milestone

A milestone at the center of the wall leaves newcomers wondering which direction earlier work belongs. Mixed day and week columns cause another problem: equal-looking gaps represent different durations.

Put the agreed milestone at the far right. Build the sequence right to left, asking what must be delivered immediately before each activity can start. Earlier dates sit farther left; elapsed time still runs left to right when you later read the plan forward. Label that distinction on the header.

A practical setup is:

  1. Mark the milestone's required date and acceptance condition at the right edge. The phase also needs a starting condition at the left boundary, so the team can tell where its responsibility begins.
  2. Draw consistent date columns and label working days, weekends and planned shutdowns. Use location lanes when several areas release separately.
  3. Place activities by an agreed date convention, such as finishing in the labeled column. Write duration on each note; note width isn't a time scale.
  4. Connect dependent IDs and record the receiving trade's needs. Put unresolved constraints in their own lane with links back to the affected cards.
  5. Read the sequence forward with the trades. Confirm overlaps, inspection time and any crew promised to simultaneous work in different locations.

Leave deliberate gaps visible. A blank column might represent curing time or unavailable access; label it rather than filling it with imaginary work. Only the trade responsible should agree to changes to its duration or commitment.

Wikipedia's “Kanban” (2025 revision) describes cards that signal material demand. A pull planning board has a different purpose: it records an agreed activity sequence and handoffs. Moving a sticky doesn't by itself authorize a crew to start. Readiness still needs checking through look-ahead planning.

Photograph the wall so another person can rebuild it

One wide phone photograph often captures the meeting but loses the plan. Small writing disappears, glare covers a date, and a loose note falls before anyone transcribes it. You can't recover a dependency from colored squares alone.

Before people leave, include the project, phase, meeting date, revision and legend on the board. Photograph the whole wall straight on, then take overlapping close-ups with column headers and lane labels visible. Open a close-up at normal viewing size and check the smallest field. If it isn't readable, retake it immediately.

Transcribe one row per activity into a shared register. Preserve its ID, trade, location, activity, duration, crew size, predecessor IDs, required conditions, release condition and agreed dates. Milestones and constraints need their own records, connected by those IDs. Don't let transcription silently rewrite the trade's wording.

Ask each trade foreman to check the entries and dependencies. Compare the register with the photographs before issuing it, especially where cards overlap. Store both under the same revision. If optical character recognition helps, treat its output as a draft; it can't infer a handoff the team never wrote.

Name one person responsible for issuing changes. Otherwise you'll have two competing plans. Date each revision and make changed cards traceable to the agreed update.

Move to digital when access and revision control require it

A remote trade partner can't point to the wall from another state. And a planner who repeatedly copies revised cards into separate files spends time reconciling records rather than resolving needs.

Those are good reasons to test digital planning. I'd move when distributed participation, frequent revisions or dependency tracking make the physical board difficult to keep current. Keep the same IDs, fields and ownership rules. Agree which record is authoritative before running a hybrid system.

Tezel, Aziz, Koskela and Tzortzopoulos (2016) examined five English highways case studies and a focus group, reporting limited visual-management implementation and significant barriers. Their findings don't establish a preferred sticky-note format or justify a software switch on their own.

Trial the digital board on one phase. Can each foreman edit their activities, see another trade's needs and discuss dependencies without the facilitator doing all the typing? If not, you've transferred the cards but lost participation.

A readable wall must produce a usable handoff

A board can look complete while “ready for drywall” means different things to adjacent trades. That disagreement deserves attention before anyone worries about the palette.

At the end, ask a receiving foreman to identify their activity, its predecessor and the condition they'll accept. If they can't, revise the relevant cards together. The agreed sequence then feeds make-ready checks and the weekly work plan, where ready assignments become specific commitments. Keep the wall readable enough that a missing condition is hard to hide.

Sources

  1. Villego (2025). Villego ® kit.
  2. Robert Warcup and Edward Reeve (2014). Using the Villego® Simulation to Teach the Last Planner® System.
  3. Wikipedia (2024). Visual control.
  4. Wikipedia (2024). Post-it note.
  5. Wikipedia (2025). Kanban.
  6. Algan Tezel, Zeeshan Aziz, Lauri Koskela and Patricia Tzortzopoulos (2016). Visual Management Condition in Highways Construction Projects in England.